Gharkul Height, Bhandup West

Lapsed

by Angath Properties LLP · Bhandup West, Mumbai 400078 · Map

Launched
Jul 20184 yrs 5 mths originally promised
Possession (MahaRERA)
Jun 2026Extended by 3 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
89 of 24137%
Buildings
10.6 acres
MahaRERA complaints
17Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
180
2 BHK
61
Total units
241
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
17

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%89
100%0%0%–
100%0%0%–
100%0%0%89

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Gharkul Height by Angath Properties LLP is a 241-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in July 2018; its MahaRERA registration has lapsed. 89 units booked out of total 241 units. Work on the concrete structure (RCC) has not started.

Read full summary

Gharkul Height is a BMC-sanctioned project by Angath Properties LLP in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800017037. It was launched in July 2018. It has 241 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026, after an extension of 3 years 6 months from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.

89 units booked out of total 241 units (37%).