Swaroop Aditya Avenue, Andheri East

Lapsed

by Swaroop Aditya Developer · Andheri East, Mumbai 400059 · Map

Launched
Jul 20185 yrs originally promised
Possession (MahaRERA)
Jun 2025Extended by 1 yr 11 mthsWhat does Lapsed mean?
Concrete structure
10%Mid-construction
Booked
96 of 17954%
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
179
Total units
179
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)10%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 10%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 10%Oct 2026: Concrete structure (RCC) 10%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 10%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%10%0%96
100%10%0%96
100%10%0%96
100%10%0%65

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Swaroop Aditya Avenue by Swaroop Aditya Developer is a 179-unit BMC-sanctioned project in Andheri East, Mumbai 400059, launched in July 2018; its MahaRERA registration has lapsed. 96 units booked out of total 179 units. The concrete structure (RCC) is 10% complete.

Read full summary

Swaroop Aditya Avenue is a BMC-sanctioned project by Swaroop Aditya Developer in Andheri East, Mumbai 400059, registered with MahaRERA as P51800017168. It was launched in July 2018. It has 179 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 1 year 11 months from the original July 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 10% complete, final finishes not started.

96 units booked out of total 179 units (54%).