Sale Building No. 14 - Phase 1, Govandi
Lapsed
by Mangal Moorti Developers Private Limited · Govandi, Mumbai 400043 · Map
- Launched
- Jul 20186 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2024Not extendedWhat does Lapsed mean?
- Concrete structure
- 0%Early stage
- Booked
- 62 of 10062%
- Buildings
- 10.9 acres
- MahaRERA complaints
- 21Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 37
- 3 BHK
- 39
- Other units
- 24
- Total units
- 100
- Buildings
- 1
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 21
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 62 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 62 |
"–" means MahaRERA shows no figure for that update.
About this project
Sale Building No. 14 - Phase 1 by Mangal Moorti Developers Private Limited is a 100-unit SRA-sanctioned project in Govandi, Mumbai 400043, launched in July 2018; its MahaRERA registration has lapsed. 62 units booked out of total 100 units. Work on the concrete structure (RCC) has not started.
Read full summary
Sale Building No. 14 - Phase 1 is an SRA-sanctioned project by Mangal Moorti Developers Private Limited in Govandi, Mumbai 400043, registered with MahaRERA as P51800017169. It was launched in July 2018. It has 100 units in 1 building: 76 homes (2 and 3 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.
62 units booked out of total 100 units (62%).