Sale Building No. 14 - Phase 1, Govandi

Lapsed

by Mangal Moorti Developers Private Limited · Govandi, Mumbai 400043 · Map

Launched
Jul 20186 yrs 5 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
62 of 10062%
Buildings
10.9 acres
MahaRERA complaints
21Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
37
3 BHK
39
Other units
24
Total units
100
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
21

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%62
100%0%0%–
100%0%0%–
100%0%0%62

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sale Building No. 14 - Phase 1 by Mangal Moorti Developers Private Limited is a 100-unit SRA-sanctioned project in Govandi, Mumbai 400043, launched in July 2018; its MahaRERA registration has lapsed. 62 units booked out of total 100 units. Work on the concrete structure (RCC) has not started.

Read full summary

Sale Building No. 14 - Phase 1 is an SRA-sanctioned project by Mangal Moorti Developers Private Limited in Govandi, Mumbai 400043, registered with MahaRERA as P51800017169. It was launched in July 2018. It has 100 units in 1 building: 76 homes (2 and 3 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.

62 units booked out of total 100 units (62%).