Auris Galleria, Malad West

Lapsed

by Transcon-Sheth Creators Private Limited · Malad West, Mumbai 400064 · Map

Launched
Jul 20185 yrs 5 mths promised
Possession (MahaRERA)
Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.5 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
105
Total units
105
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 75%Dec 2025: Final finishes 75%Jul 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%–
100%100%75%–
100%100%75%99

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Auris Galleria by Transcon-Sheth Creators Private Limited is a 105-unit project in Malad West, Mumbai 400064, launched in July 2018; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Auris Galleria is a project by Transcon-Sheth Creators Private Limited in Malad West, Mumbai 400064, registered with MahaRERA as P51800017171. It was launched in July 2018. It has 105 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

Transcon's track record in Mumbai

MahaRERA projects registered 2017–2024 in Mumbai

Projects registered with MahaRERA14
Total units across these projects4,175
Completed without extending the possession date3
Completed after an extension0
Lapsed3
Under construction8
Possession date extended on the builder's application2
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Transcon projects156 (13 of 14 projects)

See all Transcon projects →