Skip to main content

Marathon Millennium, Mulund West

Lapsed

by Terrapolis Assets Pvt Ltd · Mulund West, Mumbai 400080 · Map

Launched
Aug 2018First of 2 phases
Possession (MahaRERA)
Jun 2024 – Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
88%Weighted across 2 phases
Booked
–
Buildings
20.3 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
405
Total units
405
Buildings
2
Land
0.3 acres
Phases
2
MahaRERA complaints
2

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Marathon Millennium 1
Ready to move Lapsed
P518000173240100%–
Marathon Millennium 2
Mid-construction Lapsed
P51800021203084%35%
Show updates by phase

Marathon Millennium 1 (P51800017324)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%92%–
100%100%92%–
100%100%92%91

"–" means MahaRERA shows no figure for that update.

Marathon Millennium 2 (P51800021203)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%84%64%103
0%84%62%103
0%84%62%86

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation26%
Concrete structure (slabs)88%
Finishes, lifts and services71%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 26%Dec 2025: Excavation 26%Jul 2026: Excavation 26%Dec 2024: Concrete structure (RCC) 88%Dec 2025: Concrete structure (RCC) 88%Jul 2026: Concrete structure (RCC) 88%Dec 2024: Final finishes 70%Dec 2025: Final finishes 70%Jul 2026: Final finishes 71%Concrete structure (RCC) 88%Final finishes 71%Excavation 26%

How to read construction stages

About this project

Marathon Millennium by Terrapolis Assets Pvt Ltd is a 405-unit BMC-sanctioned project in Mulund West, Mumbai 400080, registered with MahaRERA in 2 phases, with possession dates from June 2024 to June 2026. The concrete structure (RCC) is 88% complete.

Read full summary

Marathon Millennium is a BMC-sanctioned project by Terrapolis Assets Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as 2 phases (P51800017324, P51800021203). The first phase was launched in August 2018. Together the phases have 405 units in 2 buildings, as registered with MahaRERA. Both phases are lapsed on MahaRERA.

The phases' registered possession dates run from June 2024 to June 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 88% complete and final finishes 71% complete. Neither phase has its structure complete.