Marathon Millennium, Mulund West
Lapsed
by Terrapolis Assets Pvt Ltd · Mulund West, Mumbai 400080 · Map
- Launched
- Aug 2018First of 2 phases
- Possession (MahaRERA)
- Jun 2024 – Jun 2026Not extendedWhat does Lapsed mean?
- Concrete structure
- 88%Weighted across 2 phases
- Booked
- –
- Buildings
- 20.3 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 405
- Total units
- 405
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 2
- MahaRERA complaints
- 2
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Marathon Millennium 1 Ready to move Lapsed | P51800017324 | 0 | 100% | – | |
| Marathon Millennium 2 Mid-construction Lapsed | P51800021203 | 0 | 84% | 35% |
Show updates by phase
Marathon Millennium 1 (P51800017324)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 92% | – | |
| 100% | 100% | 92% | – | |
| 100% | 100% | 92% | 91 |
"–" means MahaRERA shows no figure for that update.
Marathon Millennium 2 (P51800021203)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 84% | 64% | 103 | |
| 0% | 84% | 62% | 103 | |
| 0% | 84% | 62% | 86 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Marathon Millennium by Terrapolis Assets Pvt Ltd is a 405-unit BMC-sanctioned project in Mulund West, Mumbai 400080, registered with MahaRERA in 2 phases, with possession dates from June 2024 to June 2026. The concrete structure (RCC) is 88% complete.
Read full summary
Marathon Millennium is a BMC-sanctioned project by Terrapolis Assets Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as 2 phases (P51800017324, P51800021203). The first phase was launched in August 2018. Together the phases have 405 units in 2 buildings, as registered with MahaRERA. Both phases are lapsed on MahaRERA.
The phases' registered possession dates run from June 2024 to June 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 88% complete and final finishes 71% complete. Neither phase has its structure complete.