Saptarshi Mark, Kurla East
by Saptrishi Realtors · Kurla East, Mumbai 400024 · Map
- Launched
- Aug 20185 yrs 4 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 3 yrs 3 mths
- Concrete structure
- 78%Mid-construction
- Booked (free sale)
- 69 of 9573% · 39 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale69 booked out of 95 units
Rehab39 units for existing members
Total 134 units. Rehab units are not for sale.
Project facts
- 1 RK
- 17
- 1 BHK
- 35
- 2 BHK
- 82
- Total units
- 134
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 95
- Rehab units
- 39
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 78% | 0% | 69 | |
| 100% | 78% | 0% | 68 | |
| 100% | 78% | 0% | – | |
| 100% | 78% | 0% | 64 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400024
Projects with 60–300 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 5 yrs 8 mths |
| Possession date extended | By 3 yrs 3 mths | 2 of 3 |
| Possession date (MahaRERA) | Mar 2027 | Jun 2025 |
| Concrete structure (RCC) | 78% | 100% |
| MahaRERA complaints (filed by or against the builder) | 1 | 10 |
The 3 projects
- Ruparel Pride, Kurla East
- Midas Bhoomi Harmony, Kurla East
- Puneet Prime Phase 2 Floor 3 To Floor 16, Kurla East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ruparel Pride | April 2019 | December 2025 | 100% | 81 units booked out of total 130 units |
| Midas Bhoomi Harmony | May 2019 | October 2021 | 100% | – |
| Puneet Prime Phase 2 Floor 3 To Floor 16 | May 2019 | June 2025 | 100% | 68 units booked out of total 68 units |
About this project
Saptarshi Mark by Saptrishi Realtors is a 134-unit MHADA-sanctioned project in Kurla East, Mumbai 400024, launched in August 2018 with possession due in March 2027. 69 units booked out of 95 units for sale. The concrete structure (RCC) is 78% complete.
Read full summary
Saptarshi Mark is a MHADA-sanctioned project by Saptrishi Realtors in Kurla East, Mumbai 400024, registered with MahaRERA as P51800017508. It was launched in August 2018. It has 134 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 134 units, 95 are for sale and 39 are rehab units for existing members.
Its registered possession date is March 2027, extended by 3 years 3 months from the original December 2023. Construction: excavation complete, structure (RCC) 78% complete, final finishes not started.
69 units booked out of 95 units for sale (73%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from December 2024 to March 2027.