Madhukunj CHSL Building No 23, Vikhroli
Lapsed
by Haroon Rashid Imtiyaz Ahmad Shaikh · Vikhroli, Mumbai 400083 · Map
- Launched
- Sep 20182 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2024Extended by 4 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 41 of 4298%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 42
- Total units
- 42
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 41 | |
| 100% | 100% | 50% | – | |
| 100% | 100% | 50% | – | |
| 100% | 100% | 50% | 41 |
"–" means MahaRERA shows no figure for that update.
About this project
Madhukunj CHSL Building No 23 by Haroon Rashid Imtiyaz Ahmad Shaikh is a 42-unit project in Vikhroli, Mumbai 400083, launched in September 2018; its MahaRERA registration has lapsed. 41 units booked out of total 42 units. The concrete structure (RCC) is complete.
Read full summary
Madhukunj CHSL Building No 23 is a project by Haroon Rashid Imtiyaz Ahmad Shaikh in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800017728. It was launched in September 2018. It has 42 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2024, after an extension of 4 years from the original December 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.
41 units booked out of total 42 units (98%).