Saraswati Heights, Mulund West
Lapsed
by Metro Builders & Developers · Mulund West, Mumbai 400080 · Map
- Launched
- Oct 20185 yrs 11 mths promised
- Possession (MahaRERA)
- Sep 2024Not extendedWhat does Lapsed mean?
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 21 of 3364% · 9 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale21 booked out of 33 units
Rehab9 units for existing members
Total 42 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 14
- 3 BHK
- 19
- 4 BHK
- 2
- Other units
- 7
- Total units
- 42
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 33
- Rehab units
- 9
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Jul 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 21 | |
| 0% | 0% | 0% | 21 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Saraswati Heights by Metro Builders & Developers is a 42-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in October 2018; its MahaRERA registration has lapsed. 21 units booked out of 33 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Saraswati Heights is an SRA-sanctioned project by Metro Builders & Developers in Mulund West, Mumbai 400080, registered with MahaRERA as P51800018327. It was launched in October 2018. It has 42 units in 2 buildings: 35 homes (2, 3 and 4 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 42 units, 33 are for sale and 9 are rehab units for existing members.
Possession was due in September 2024. That date has passed and no extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.
21 units booked out of 33 units for sale (64%).