Swashray, Borivali West

Lapsed

by Shanti Enterprise · Borivali West, Mumbai 400092 · Map

Launched
Nov 20183 yrs 6 mths originally promised
Possession (MahaRERA)
Dec 2022Extended by 7 mthsWhat does Lapsed mean?
Concrete structure
90%Mid-construction
Booked
12 of 3139%
Buildings
10.1 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
15
Other units
16
Total units
31
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 90%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%50%12
100%90%50%–
100%90%50%–
100%90%50%12

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Swashray by Shanti Enterprise is a 31-unit project in Borivali West, Mumbai 400092, launched in November 2018; its MahaRERA registration has lapsed. 12 units booked out of total 31 units. The concrete structure (RCC) is 90% complete.

Read full summary

Swashray is a project by Shanti Enterprise in Borivali West, Mumbai 400092, registered with MahaRERA as P51800018547. It was launched in November 2018. It has 31 units in 1 building: 15 homes (1 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2022, after an extension of 7 months from the original May 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes 50% complete.

12 units booked out of total 31 units (39%).