Alpine Building, Andheri West
Lapsed
by Milan Interbuilt Private Limited · Andheri West, Mumbai 400058 · Map
- Launched
- Nov 20182 yrs 7 mths originally promised
- Possession (MahaRERA)
- Mar 2023Extended by 1 yr 9 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 13 of 2454%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 12
- 1 BHK
- 12
- Total units
- 24
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 40% | 13 | |
| 100% | 100% | 40% | – | |
| 100% | 100% | 40% | – | |
| 100% | 100% | 40% | 13 |
"–" means MahaRERA shows no figure for that update.
About this project
Alpine Building by Milan Interbuilt Private Limited is a 24-unit project in Andheri West, Mumbai 400058, launched in November 2018; its MahaRERA registration has lapsed. 13 units booked out of total 24 units. The concrete structure (RCC) is complete.
Read full summary
Alpine Building is a project by Milan Interbuilt Private Limited in Andheri West, Mumbai 400058, registered with MahaRERA as P51800018586. It was launched in November 2018. It has 24 units in 1 building, with 1 RK and 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in March 2023, after an extension of 1 year 9 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.
13 units booked out of total 24 units (54%).