Bellissimo Mulund T2, Mulund East
by Lodha Developers Limited · Mulund East, Mumbai 400081 · Map
- Launched
- Dec 20188 yrs originally promised
- Possession (MahaRERA)
- Jun 2027Extended by 6 mths
- Concrete structure
- 100%Nearing possession
- Booked
- 132 of 24953% · 58 in Jul 2026
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 143
- 3 BHK
- 104
- Other units
- 2
- Total units
- 249
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 30% | 132 | |
| 100% | 100% | 0% | 58 | |
| 100% | 80% | 0% | 58 | |
| 100% | 20% | 0% | 47 |
"–" means MahaRERA shows no figure for that update.
About this project
Bellissimo Mulund T2 by Lodha Developers Limited is a 249-unit SRA-sanctioned project in Mulund East, Mumbai 400081, launched in December 2018 with possession due in June 2027. 132 units booked out of total 249 units. The concrete structure (RCC) is complete.
Read full summary
Bellissimo Mulund T2 is an SRA-sanctioned project by Lodha Developers Limited in Mulund East, Mumbai 400081, registered with MahaRERA as P51800018893. It was launched in December 2018. It has 249 units in 1 building: 247 homes (2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2027, extended by 6 months from the original December 2026. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.
132 units booked out of total 249 units (53%). Since the July 2026 update, 74 more units have been booked.
Lodha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 85 |
|---|---|
| Total units across these projects | 15,101 |
| Completed without extending the possession date | 31 |
| Completed after an extension | 13 |
| Lapsed | 0 |
| Under construction | 41 |
| Possession date extended on the builder's application | 34 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Lodha projects | 242 (38 of 85 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.