Lodha projects in Mumbai
MahaRERA projects by Lodha registered 2017–2026 in Mumbai.
| Projects registered with MahaRERA | 85 |
|---|---|
| Total units across these projects | 15,101 |
Full record
MahaRERA projects registered 2017–2026 in Mumbai
| Completed without extending the possession date | 31 |
|---|---|
| Completed after an extension | 13 |
| Lapsed | 0 |
| Under construction | 41 |
| Possession date extended on the builder's application | 34 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Lodha projects | 242 (38 of 85 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Sion (15) · Lower Parel (9) · Andheri East (7) · Vikhroli (5) · Kandivali East (4) · Kalachowki (3) · Malabar Hill (3) · Jogeshwari West (2) · Mulund East (2) · Mahalaxmi (2)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Acenza · 3 phases | Andheri East | Mid-construction | May 2027 – Dec 2029 | 110 units booked out of total 241 units |
| Altus | Borivali West | Mid-construction | December 2030 | 169 units booked out of total 204 units |
| Aureus | Sewri | Early stage | December 2032 | 0 units booked out of total 354 units |
| Bellevue Tower - 3 | Mahalaxmi | Nearing possession | December 2027 | 172 units booked out of total 231 units |
| Bellissimo Matunga · 4 phases | Sion | Mid-construction | Dec 2027 – Mar 2030 | 486 units booked out of total 664 units |
| Bellissimo Mulund T2 | Mulund East | Nearing possession | June 2027 | 132 units booked out of total 249 units |
| Corinthia · 3 phases | Bhandup West | Mid-construction | May 2031 – Nov 2031 | 346 units booked out of total 621 units |
| Cullinan | Versova | Nearing possession | December 2028 | 5 units booked out of total 41 units |
| Lodha Bellevue | Mahalaxmi | Nearing possession | September 2028 | 326 units booked out of total 360 units |
| Lodha Kandivali Project · 2 phases | Kandivali East | Nearing possession | Feb 2028 | 233 units booked out of total 241 units |
| Lodha Malabar | Malabar Hill | Mid-construction | June 2027 | 25 units booked out of total 29 units |
| Lodha Matunga | Sion | Mid-construction | April 2028 | 47 units booked out of total 58 units |
| Lodha NCP · 2 phases | Sion | Mid-construction | Jun 2030 | 285 units booked out of total 445 units |
| Lodha Vikhroli - Tower C1 | Vikhroli | Mid-construction | December 2028 | 178 units booked out of total 224 units |
| Lodha Vikhroli-Signet | Vikhroli | Mid-construction | June 2029 | 642 units booked out of total 907 units |
| Lodha Woods · 3 phases | Kandivali East | Mid-construction | Nov 2027 – Nov 2028 | 281 units booked out of total 287 units |
| Lodha Worli Residential Project | Prabhadevi | Early stage | June 2033 | 0 units booked out of total 195 units |
| Marq | Grant Road | Mid-construction | November 2028 | 44 units booked out of total 81 units |
| Matunga Signet | Sion | Early stage | September 2029 | 228 units booked out of total 267 units |
| Matunga Wing B | Sion | Nearing possession | March 2029 | 34 units booked out of total 59 units |
| Promina | Prabhadevi | Early stage | October 2032 | 0 units booked out of total 28 units |
| Sea Face | Worli | Mid-construction | February 2029 | 9 units booked out of total 29 units |
| Sovrano · 3 phases | Jogeshwari West | Early stage | Dec 2030 – Mar 2031 | 58 units booked out of total 360 units |
| Vikhroli ASPI Project · 4 phases | Vikhroli | Mid-construction | Jan 2029 – Dec 2030 | 323 units booked out of total 488 units |
| Vikhroli Premium Tower A1 | Vikhroli | Early stage | December 2030 | 0 units booked out of total 124 units |
| Vikhroli Tower C3 | Vikhroli | Nearing possession | December 2029 | 151 units booked out of total 432 units |
| Waterview | Malabar Hill | Mid-construction | June 2028 | 3 units booked out of total 11 units |
| Woods Tower 9 | Kandivali East | Early stage | December 2029 | 14 units booked out of total 32 units |
Completed
| Project | Village | Status |
|---|---|---|
| Lodha Adrina | Lower Parel | Completed |
| Lodha Azzuro | Kalachowki | Completed |
| Lodha Bellagio | Powai | Completed |
| Lodha Eternis Idyllia A | Andheri East | Completed |
| Lodha Eternis Idyllia B, Serena B, Natura B And C | Andheri East | Completed |
| Lodha Eternis Natura A | Andheri East | Completed |
| Lodha Eternis Serena A | Andheri East | Completed |
| Lodha Eternis Serena C | Andheri East | Completed |
| Lodha Fiorenza | Goregaon East | Completed |
| Lodha Kandivali Project | Kandivali East | Completed |
| Lodha Lower Parel Project | Lower Parel | Completed |
| Lodha Mulund Project | Mulund East | Completed |
| Lodha Parel Project | Parel | Completed |
| Lodha Park | Lower Parel | Completed |
| Lodha Patel Estate | Jogeshwari West | Completed |
| Lodha Seaview | Malabar Hill | Completed |
| Lodha Signet Lower Parel | Lower Parel | Completed |
| Lodha Supremus | Andheri East | Completed |
| Lodha Venezia | Kalachowki | Completed |
| NCP Commercial | Sion | Completed |
| New Cuffe Parade | Sion | Completed |
| One Lodha Place | Lower Parel | Completed |
| The World | Lower Parel | Completed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.