Lapsed

by Vastav Developers Pvt Ltd · Bhandup East, Mumbai 400042 · Map

Launched
Dec 20183 yrs 10 mths originally promised
Possession (MahaRERA)
Jul 2024Extended by 1 yr 9 mthsWhat does Lapsed mean?
Concrete structure
81%Mid-construction
Booked
24 of 2596%
Buildings
10.2 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
12
2 BHK
13
Total units
25
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)81%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 81%Dec 2025: Concrete structure (RCC) 81%Jul 2026: Concrete structure (RCC) 81%Oct 2026: Concrete structure (RCC) 81%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 81%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%81%0%24
100%81%0%–
100%81%0%–
100%81%0%24

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Meghmanisha by Vastav Developers Pvt Ltd is a 25-unit project in Bhandup East, Mumbai 400042, launched in December 2018; its MahaRERA registration has lapsed. 24 units booked out of total 25 units. The concrete structure (RCC) is 81% complete.

Read full summary

Meghmanisha is a project by Vastav Developers Pvt Ltd in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800018919. It was launched in December 2018. It has 25 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in July 2024, after an extension of 1 year 9 months from the original October 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 81% complete, final finishes not started.

24 units booked out of total 25 units (96%).