Sharda Pristine, Mulund West

Lapsed

by Anuwrita Realty Private Limited · Mulund West, Mumbai 400080 · Map

Launched
Dec 20184 yrs 9 mths promised
Possession (MahaRERA)
Sep 2023Not extendedWhat does Lapsed mean?
Concrete structure
90%Mid-construction
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
8
3 BHK
12
Other units
4
Total units
24
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services22%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 22%Dec 2025: Final finishes 22%Jul 2026: Final finishes 22%Excavation 100%Concrete structure (RCC) 90%Final finishes 22%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%22%–
100%90%22%–
100%90%22%9

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sharda Pristine by Anuwrita Realty Private Limited is a 24-unit project in Mulund West, Mumbai 400080, launched in December 2018; its MahaRERA registration has lapsed. The concrete structure (RCC) is 90% complete.

Read full summary

Sharda Pristine is a project by Anuwrita Realty Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800018974. It was launched in December 2018. It has 24 units in 1 building: 20 homes (2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes 22% complete.