Ndw Altima, Andheri East

Lapsed

by Aviation Hotels Pvt Ltd · Andheri East, Mumbai 400059 · Map

Launched
Jan 20194 yrs 11 mths promised
Possession (MahaRERA)
Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
33 of 33100%
Buildings
10.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
33
Total units
33
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation70%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 70%Dec 2025: Excavation 70%Jul 2026: Excavation 70%Oct 2026: Excavation 70%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 70%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%0%0%33
70%0%0%–
70%0%0%–
70%0%0%33

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ndw Altima by Aviation Hotels Pvt Ltd is a 33-unit BMC-sanctioned project in Andheri East, Mumbai 400059, launched in January 2019; its MahaRERA registration has lapsed. 33 units booked out of total 33 units. Work on the concrete structure (RCC) has not started.

Read full summary

Ndw Altima is a BMC-sanctioned project by Aviation Hotels Pvt Ltd in Andheri East, Mumbai 400059, registered with MahaRERA as P51800019228. It was launched in January 2019. It has 33 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation 70% complete, structure (RCC) not started, final finishes not started.

33 units booked out of total 33 units (100%).