Manthan Galaxy, Chembur

Lapsed

by Swastik Manthan Jv · Chembur, Mumbai 400089 · Map

Launched
Jan 20196 yrs 11 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
14 of 5028%
Buildings
10.7 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
3
2 BHK
26
3 BHK
20
4 BHK
1
Total units
50
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services65%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 65%Jul 2026: Final finishes 65%Oct 2026: Final finishes 65%Excavation 100%Concrete structure (RCC) 100%Final finishes 65%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%65%14
100%100%65%–
100%100%65%–
90%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Manthan Galaxy by Swastik Manthan Jv is a 50-unit BMC-sanctioned project in Chembur, Mumbai 400089, launched in January 2019; its MahaRERA registration has lapsed. 14 units booked out of total 50 units. The concrete structure (RCC) is complete.

Read full summary

Manthan Galaxy is a BMC-sanctioned project by Swastik Manthan Jv in Chembur, Mumbai 400089, registered with MahaRERA as P51800019271. It was launched in January 2019. It has 50 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 65% complete.

14 units booked out of total 50 units (28%).