Skip to main content

Angel View, Bandra West

Ready to moveLapsed

by K .K.Constructions · Bandra West, Mumbai 400050 · Map

Launched
Feb 20193 yrs 1 mth originally promised
Possession (MahaRERA)
Dec 2024Extended by 2 yrs 9 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
8 of 1173%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
11
Total units
11
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%8
100%100%90%–
100%100%90%–
100%100%90%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Angel View by K .K.Constructions is an 11-unit project in Bandra West, Mumbai 400050, launched in February 2019; its MahaRERA registration has lapsed. 8 units booked out of total 11 units. The concrete structure (RCC) is complete.

Read full summary

Angel View is a project by K .K.Constructions in Bandra West, Mumbai 400050, registered with MahaRERA as P51800019516. It was launched in February 2019. It has 11 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 2 years 9 months from the original March 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

8 units booked out of total 11 units (73%).