Commerz 54, Santacruz West

Lapsed

by Shree Vinayak Reality Private Limited · Santacruz West, Mumbai 400054 · Map

Launched
Mar 20193 yrs 9 mths originally promised
Possession (MahaRERA)
Oct 2026Extended by 3 yrs 10 mthsWhat does Lapsed mean?
Concrete structure
80%Mid-construction
Booked
39 of 11135%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
111
Total units
111
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 83%Jul 2026: Concrete structure (RCC) 83%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 0%Dec 2025: Final finishes 25%Jul 2026: Final finishes 25%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 80%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%20%39
100%83%25%39
100%83%25%39
100%0%0%42

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Commerz 54 by Shree Vinayak Reality Private Limited is a 111-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in March 2019; its MahaRERA registration has lapsed. 39 units booked out of total 111 units. The concrete structure (RCC) is 80% complete.

Read full summary

Commerz 54 is a BMC-sanctioned project by Shree Vinayak Reality Private Limited in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800020069. It was launched in March 2019. It has 111 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Its registered possession date is October 2026, extended by 3 years 10 months from the original December 2022. Construction: excavation complete, structure (RCC) 80% complete, final finishes 20% complete.

39 units booked out of total 111 units (35%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 83% to 80% and the possession date has moved from December 2023 to October 2026.