Shreejee Mrugarchana Chs Ltd, Mulund West

Lapsed

by Shreejee Buildcon Homes LLP · Mulund West, Mumbai 400080 · Map

Launched
Apr 20193 yrs 11 mths originally promised
Possession (MahaRERA)
Jul 2025Extended by 2 yrs 4 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked (free sale)
39 of 4195% · 41 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale39 booked out of 41 units

Rehab41 units for existing members

Total 82 units. Rehab units are not for sale.

Project facts

2 BHK
64
3 BHK
17
4 BHK
1
Total units
82
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
41
Rehab units
41

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services86%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 66%Dec 2025: Final finishes 66%Jul 2026: Final finishes 66%Oct 2026: Final finishes 86%Excavation 100%Concrete structure (RCC) 100%Final finishes 86%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%86%39
100%100%66%–
100%100%66%–
100%100%66%39

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shreejee Mrugarchana Chs Ltd by Shreejee Buildcon Homes LLP is an 82-unit project in Mulund West, Mumbai 400080, launched in April 2019; its MahaRERA registration has lapsed. 39 units booked out of 41 units for sale. The concrete structure (RCC) is complete.

Read full summary

Shreejee Mrugarchana Chs Ltd is a project by Shreejee Buildcon Homes LLP in Mulund West, Mumbai 400080, registered with MahaRERA as P51800020300. It was launched in April 2019. It has 82 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 82 units, 41 are for sale and 41 are rehab units for existing members.

Possession was due in July 2025, after an extension of 2 years 4 months from the original March 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 86% complete.

39 units booked out of 41 units for sale (95%).