- Launched
- Apr 20194 yrs 8 mths originally promised
- Possession (MahaRERA)
- Jul 2026Extended by 2 yrs 7 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 47 of 8158% · 29 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale47 booked out of 81 units
Rehab29 units for existing members
Total 110 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 18
- 2 BHK
- 64
- 3 BHK
- 28
- Total units
- 110
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 81
- Rehab units
- 29
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 47 | |
| 100% | 100% | 80% | 47 | |
| 100% | 100% | 80% | 47 | |
| 100% | 100% | 80% | 18 |
"–" means MahaRERA shows no figure for that update.
About this project
Madhuban by Je And Vee Infrastructure is a 110-unit MHADA-sanctioned project in Malad East, Mumbai 400097, launched in April 2019; its MahaRERA registration has lapsed. 47 units booked out of 81 units for sale. The concrete structure (RCC) is complete.
Read full summary
Madhuban is a MHADA-sanctioned project by Je And Vee Infrastructure in Malad East, Mumbai 400097, registered with MahaRERA as P51800020431. It was launched in April 2019. It has 110 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 110 units, 81 are for sale and 29 are rehab units for existing members.
Possession was due in July 2026, after an extension of 2 years 7 months from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.
47 units booked out of 81 units for sale (58%).