Datta Vijay Chs Ltd, Mulund East

Lapsed

by Vastav Buildcon · Mulund East, Mumbai 400081 · Map

Launched
Apr 20194 yrs 2 mths originally promised
Possession (MahaRERA)
Jun 2024Extended by 1 yrWhat does Lapsed mean?
Concrete structure
53%Mid-construction
Booked
–
Buildings
20.5 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
14
3 BHK
17
Other units
14
Total units
45
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)53%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 53%Dec 2025: Concrete structure (RCC) 53%Jul 2026: Concrete structure (RCC) 53%Dec 2024: Final finishes 25%Dec 2025: Final finishes 25%Jul 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 53%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%53%25%–
100%53%25%–
100%53%25%43

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Datta Vijay Chs Ltd by Vastav Buildcon is a 45-unit project in Mulund East, Mumbai 400081, launched in April 2019; its MahaRERA registration has lapsed. The concrete structure (RCC) is 53% complete.

Read full summary

Datta Vijay Chs Ltd is a project by Vastav Buildcon in Mulund East, Mumbai 400081, registered with MahaRERA as P51800020474. It was launched in April 2019. It has 45 units in 2 buildings: 31 homes (2 and 3 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2024, after an extension of 1 year from the original June 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 53% complete, final finishes 25% complete.