Puneet Prime Phase 3 Floor 17 To Floor 18, Kurla East
Lapsed
by Puneet Builders · Kurla East, Mumbai 400024 · Map
- Launched
- May 20196 yrs 1 mth promised
- Possession (MahaRERA)
- Jun 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 8 of 8100%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 2
- 2 BHK
- 6
- Total units
- 8
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 6% | 8 | |
| 100% | 100% | 6% | – | |
| 100% | 100% | 6% | – | |
| 100% | 100% | 6% | 8 |
"–" means MahaRERA shows no figure for that update.
About this project
Puneet Prime Phase 3 Floor 17 To Floor 18 by Puneet Builders is an 8-unit MHADA-sanctioned project in Kurla East, Mumbai 400024, launched in May 2019; its MahaRERA registration has lapsed. 8 units booked out of total 8 units. The concrete structure (RCC) is complete.
Read full summary
Puneet Prime Phase 3 Floor 17 To Floor 18 is a MHADA-sanctioned project by Puneet Builders in Kurla East, Mumbai 400024, registered with MahaRERA as P51800020793. It was launched in May 2019. It has 8 units in 1 building, with 1 RK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 6% complete.
8 units booked out of total 8 units (100%).