Puneet Prime Phase 1 Floor 0 To Floor 2, Kurla East
Lapsed
by Puneet Builders · Kurla East, Mumbai 400024 · Map
- Launched
- May 20196 yrs 1 mth promised
- Possession (MahaRERA)
- Jun 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 4 of 3013%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 30
- Total units
- 30
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 5% | 4 | |
| 100% | 100% | 5% | – | |
| 100% | 100% | 5% | – | |
| 100% | 100% | 5% | 4 |
"–" means MahaRERA shows no figure for that update.
About this project
Puneet Prime Phase 1 Floor 0 To Floor 2 by Puneet Builders is a 30-unit project in Kurla East, Mumbai 400024, launched in May 2019; its MahaRERA registration has lapsed. 4 units booked out of total 30 units. The concrete structure (RCC) is complete.
Read full summary
Puneet Prime Phase 1 Floor 0 To Floor 2 is a project by Puneet Builders in Kurla East, Mumbai 400024, registered with MahaRERA as P51800020798. It was launched in May 2019. It has 30 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 5% complete.
4 units booked out of total 30 units (13%).