Iconic Residency, Kurla West

Lapsed

by S K Housing · Kurla West, Mumbai 400070 · Map

Launched
May 20194 yrs 10 mths originally promised
Possession (MahaRERA)
Jul 2026Extended by 2 yrs 4 mthsWhat does Lapsed mean?
Concrete structure
92%Mid-construction
Booked (free sale)
32 of 4276% · 32 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale32 booked out of 42 units

Rehab32 units for existing members

Total 74 units. Rehab units are not for sale.

Project facts

1 BHK
11
2 BHK
27
3 BHK
28
Other units
8
Total units
74
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
42
Rehab units
32

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)92%
Finishes, lifts and services65%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 58%Dec 2025: Concrete structure (RCC) 58%Jul 2026: Concrete structure (RCC) 58%Oct 2026: Concrete structure (RCC) 92%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 65%Excavation 100%Concrete structure (RCC) 92%Final finishes 65%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%65%32
100%58%0%25
100%58%0%25
100%58%0%18

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Iconic Residency by S K Housing is a 74-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in May 2019; its MahaRERA registration has lapsed. 32 units booked out of 42 units for sale. The concrete structure (RCC) is 92% complete.

Read full summary

Iconic Residency is a BMC-sanctioned project by S K Housing in Kurla West, Mumbai 400070, registered with MahaRERA as P51800020830. It was launched in May 2019. It has 74 units in 1 building: 66 homes (1, 2 and 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 74 units, 42 are for sale and 32 are rehab units for existing members.

Possession was due in July 2026, after an extension of 2 years 4 months from the original March 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 92% complete, final finishes 65% complete.

32 units booked out of 42 units for sale (76%). Since the July 2026 update, 7 more units have been booked, the reported concrete structure (RCC) has gone from 58% to 92% and the possession date has moved from March 2025 to July 2026.