Shree Vasari Hill Sale Building, Goregaon West

Lapsed

by Shree Laxmidevi Developers · Goregaon West, Mumbai 400104 · Map

Launched
May 20192 yrs 7 mths originally promised
Possession (MahaRERA)
Aug 2022Extended by 8 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.8 acres
MahaRERA complaints
10Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
62
4 BHK
23
Total units
85
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%–
100%100%0%–
100%100%0%72

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shree Vasari Hill Sale Building by Shree Laxmidevi Developers is an 85-unit project in Goregaon West, Mumbai 400104, launched in May 2019; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Shree Vasari Hill Sale Building is a project by Shree Laxmidevi Developers in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800020965. It was launched in May 2019. It has 85 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in August 2022, after an extension of 8 months from the original December 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.