86 Central A, Ghatkopar West

Lapsed

by Sri Sai Nidhi Realtors Private Limited · Ghatkopar West, Mumbai 400086 · Map

Launched
Jun 20195 yrs 6 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
184 of 19097%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
190
Total units
190
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 30%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 100%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%184
100%100%30%–
100%100%30%–
100%100%30%184

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

86 Central A by Sri Sai Nidhi Realtors Private Limited is a 190-unit project in Ghatkopar West, Mumbai 400086, launched in June 2019; its MahaRERA registration has lapsed. 184 units booked out of total 190 units. The concrete structure (RCC) is complete.

Read full summary

86 Central A is a project by Sri Sai Nidhi Realtors Private Limited in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800021290. It was launched in June 2019. It has 190 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.

184 units booked out of total 190 units (97%).