Runwal Pinnacle, Mulund West

by Runwal Enterprises Limited · Mulund West, Mumbai 400080 · Map

Launched
Jun 20197 yrs originally promised
Possession (MahaRERA)
Dec 2028Extended by 2 yrs 6 mths
Concrete structure
80%Mid-construction
Booked
650 of 1,10759%
Buildings
51.2 acres
MahaRERA complaints
8Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
364
2 BHK
440
3 BHK
302
Total units
1,107
Buildings
5
Land
1.2 acres
Phases
1
MahaRERA complaints
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services5%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 26%Dec 2025: Concrete structure (RCC) 54%Jul 2026: Concrete structure (RCC) 65%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 0%Dec 2025: Final finishes 2%Jul 2026: Final finishes 3%Oct 2026: Final finishes 5%Excavation 100%Concrete structure (RCC) 80%Final finishes 5%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%5%650
100%65%3%–
100%54%2%–
100%26%0%650

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Runwal Pinnacle by Runwal Enterprises Limited is a 1,107-unit project in Mulund West, Mumbai 400080, launched in June 2019 with possession due in December 2028. 650 units booked out of total 1,107 units. The concrete structure (RCC) is 80% complete.

Read full summary

Runwal Pinnacle is a project by Runwal Enterprises Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800021322. It was launched in June 2019. It has 1,107 units in 5 buildings, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, extended by 2 years 6 months from the original June 2026. Construction: excavation complete, structure (RCC) 80% complete, final finishes 5% complete.

650 units booked out of total 1,107 units (59%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 65% to 80% and the possession date has moved from June 2027 to December 2028.

Runwal's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA46
Total units across these projects14,623
Completed without extending the possession date10
Completed after an extension5
Lapsed5
Under construction26
Possession date extended on the builder's application16
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Runwal projects343 (35 of 46 projects)

See all Runwal projects →