Navrang Oasis, Jogeshwari West
Lapsed
by Oxford Realtors (India) PvtLtd · Jogeshwari West, Mumbai 400102 · Map
- Launched
- Jun 20193 yrs 5 mths originally promised
- Possession (MahaRERA)
- Apr 2025Extended by 2 yrs 5 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 102 of 12482%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 4Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 68
- 2 BHK
- 40
- 3 BHK
- 3
- Other units
- 13
- Total units
- 124
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 53% | 102 | |
| 100% | 100% | 53% | 102 | |
| 100% | 100% | 53% | 102 | |
| 100% | 100% | 43% | 97 |
"–" means MahaRERA shows no figure for that update.
About this project
Navrang Oasis by Oxford Realtors (India) PvtLtd is a 124-unit MHADA-sanctioned project in Jogeshwari West, Mumbai 400102, launched in June 2019; its MahaRERA registration has lapsed. 102 units booked out of total 124 units. The concrete structure (RCC) is complete.
Read full summary
Navrang Oasis is a MHADA-sanctioned project by Oxford Realtors (India) PvtLtd in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800021423. It was launched in June 2019. It has 124 units in 1 building: 111 homes (1, 2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in April 2025, after an extension of 2 years 5 months from the original November 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 53% complete.
102 units booked out of total 124 units (82%).