Innoventures, Ghatkopar West
Lapsed
by Innoventures Infrastructure Pvt Ltd · Ghatkopar West, Mumbai 400086 · Map
- Launched
- Jul 20195 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2024Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 8 of 6113%
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 9
- 2 BHK
- 43
- 5+ BHK
- 9
- Total units
- 61
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | 8 | |
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | 8 |
"–" means MahaRERA shows no figure for that update.
About this project
Innoventures by Innoventures Infrastructure Pvt Ltd is a 61-unit project in Ghatkopar West, Mumbai 400086, launched in July 2019; its MahaRERA registration has lapsed. 8 units booked out of total 61 units. The concrete structure (RCC) is complete.
Read full summary
Innoventures is a project by Innoventures Infrastructure Pvt Ltd in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800021453. It was launched in July 2019. It has 61 units in 1 building, with 1, 2 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.
8 units booked out of total 61 units (13%).