- Launched
- Jul 20196 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 44 of 6865%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 43
- 2 BHK
- 24
- Other units
- 1
- Total units
- 68
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 60% | 44 | |
| 100% | 100% | 60% | – | |
| 100% | 100% | 60% | – | |
| 100% | 100% | 60% | 44 |
"–" means MahaRERA shows no figure for that update.
About this project
S3 Proxima by S3 Formeet Realtors LLP is a 68-unit MHADA-sanctioned project in Chembur, Mumbai 400089, launched in July 2019; its MahaRERA registration has lapsed. 44 units booked out of total 68 units. The concrete structure (RCC) is complete.
Read full summary
S3 Proxima is a MHADA-sanctioned project by S3 Formeet Realtors LLP in Chembur, Mumbai 400089, registered with MahaRERA as P51800021526. It was launched in July 2019. It has 68 units in 1 building: 67 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.
44 units booked out of total 68 units (65%).