Avant Heera Complex, Jogeshwari East

Lapsed

by Avant Jakhar Natural Resources LLP · Jogeshwari East, Mumbai 400060 · Map

Launched
Sep 20194 yrs 3 mths promised
Possession (MahaRERA)
Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
60%Mid-construction
Booked
–
Buildings
10.9 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
9
1 BHK
8
Other units
6
Total units
23
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services65%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 60%Dec 2024: Final finishes 65%Dec 2025: Final finishes 65%Jul 2026: Final finishes 65%Excavation 100%Final finishes 65%Concrete structure (RCC) 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%65%–
100%60%65%–
100%60%65%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Avant Heera Complex by Avant Jakhar Natural Resources LLP is a 23-unit project in Jogeshwari East, Mumbai 400060, launched in September 2019; its MahaRERA registration has lapsed. The concrete structure (RCC) is 60% complete.

Read full summary

Avant Heera Complex is a project by Avant Jakhar Natural Resources LLP in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800022151. It was launched in September 2019. It has 23 units in 1 building: 17 homes (1 RK and 1 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 60% complete, final finishes 65% complete.