Sheetal Grandeur, Santacruz East
Lapsed
by D.G. Land Developers Private Limited · Santacruz East, Mumbai 400055 · Map
- Launched
- Nov 20193 yrs 11 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 2 yrs 2 mthsWhat does Lapsed mean?
- Concrete structure
- 81%Mid-construction
- Booked
- 31 of 3491%
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 5
- 2 BHK
- 22
- 3 BHK
- 7
- Total units
- 34
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 81% | 30% | 31 | |
| 100% | 81% | 30% | – | |
| 100% | 81% | 30% | – | |
| 100% | 81% | 30% | 31 |
"–" means MahaRERA shows no figure for that update.
About this project
Sheetal Grandeur by D.G. Land Developers Private Limited is a 34-unit project in Santacruz East, Mumbai 400055, launched in November 2019; its MahaRERA registration has lapsed. 31 units booked out of total 34 units. The concrete structure (RCC) is 81% complete.
Read full summary
Sheetal Grandeur is a project by D.G. Land Developers Private Limited in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800022875. It was launched in November 2019. It has 34 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025, after an extension of 2 years 2 months from the original October 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 81% complete, final finishes 30% complete.
31 units booked out of total 34 units (91%).