S.K.Milan Residency, Kurla West

Lapsed

by S.K.Construction · Kurla West, Mumbai 400070 · Map

Launched
Nov 20193 yrs 4 mths originally promised
Possession (MahaRERA)
Mar 2024Extended by 1 yrWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
2
1 BHK
10
2 BHK
1
Other units
2
Total units
15
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%–
0%0%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

S.K.Milan Residency by S.K.Construction is a 15-unit project in Kurla West, Mumbai 400070, launched in November 2019; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.

Read full summary

S.K.Milan Residency is a project by S.K.Construction in Kurla West, Mumbai 400070, registered with MahaRERA as P51800022943. It was launched in November 2019. It has 15 units in 1 building: 13 homes (1 RK, 1 BHK and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2024, after an extension of 1 year from the original March 2023. That date has passed and no further extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.