Yashomati Chsl, Chembur

Lapsed

by Samrat Enterprise · Chembur, Mumbai 400071 · Map

Launched
Nov 20193 yrs 1 mth originally promised
Possession (MahaRERA)
Dec 2024Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
4 of 944%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
9
Total units
9
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%4
100%100%50%4
100%100%50%4

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Yashomati Chsl by Samrat Enterprise is a 9-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in November 2019; its MahaRERA registration has lapsed. 4 units booked out of total 9 units. The concrete structure (RCC) is complete.

Read full summary

Yashomati Chsl is a MHADA-sanctioned project by Samrat Enterprise in Chembur, Mumbai 400071, registered with MahaRERA as P51800023057. It was launched in November 2019. It has 9 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 2 years from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

4 units booked out of total 9 units (44%).