- Launched
- Nov 20195 yrs 1 mth promised
- Possession (MahaRERA)
- Dec 2024Not extendedWhat does Lapsed mean?
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 5 of 1338% · 3 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 13 units
Rehab3 units for existing members
Total 16 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 5
- 3 BHK
- 2
- 4 BHK
- 9
- Total units
- 16
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 13
- Rehab units
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 0% | 5 | |
| 100% | 80% | 0% | – | |
| 100% | 80% | 0% | – | |
| 100% | 80% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Shrishti by Dhruva Mahendra Rathod is a 16-unit project in Khar West, Mumbai 400052, launched in November 2019; its MahaRERA registration has lapsed. 5 units booked out of 13 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Shrishti is a project by Dhruva Mahendra Rathod in Khar West, Mumbai 400052, registered with MahaRERA as P51800023092. It was launched in November 2019. It has 16 units in 1 building, with 1, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 16 units, 13 are for sale and 3 are rehab units for existing members.
Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.
5 units booked out of 13 units for sale (38%).