by Dhruva Mahendra Rathod · Khar West, Mumbai 400052 · Map

Launched
Nov 20195 yrs 1 mth promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
80%Mid-construction
Booked (free sale)
5 of 1338% · 3 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 13 units

Rehab3 units for existing members

Total 16 units. Rehab units are not for sale.

Project facts

1 BHK
5
3 BHK
2
4 BHK
9
Total units
16
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
13
Rehab units
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 80%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%0%5
100%80%0%–
100%80%0%–
100%80%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shrishti by Dhruva Mahendra Rathod is a 16-unit project in Khar West, Mumbai 400052, launched in November 2019; its MahaRERA registration has lapsed. 5 units booked out of 13 units for sale. The concrete structure (RCC) is 80% complete.

Read full summary

Shrishti is a project by Dhruva Mahendra Rathod in Khar West, Mumbai 400052, registered with MahaRERA as P51800023092. It was launched in November 2019. It has 16 units in 1 building, with 1, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 16 units, 13 are for sale and 3 are rehab units for existing members.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.

5 units booked out of 13 units for sale (38%).