Prabhat, Ghatkopar East
Lapsed
by Shivam Parivar Developers Pvt Ltd · Ghatkopar East, Mumbai 400075 · Map
- Launched
- Jan 20203 yrs 11 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 52%Mid-construction
- Booked (free sale)
- 47 of 6968% · 32 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale47 booked out of 69 units
Rehab32 units for existing members
Total 101 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 19
- 2 BHK
- 82
- Total units
- 101
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 69
- Rehab units
- 32
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 52% | 3% | 47 | |
| 100% | 52% | 3% | – | |
| 100% | 52% | 3% | – | |
| 100% | 15% | 0% | 48 |
"–" means MahaRERA shows no figure for that update.
About this project
Prabhat by Shivam Parivar Developers Pvt Ltd is a 101-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400075, launched in January 2020; its MahaRERA registration has lapsed. 47 units booked out of 69 units for sale. The concrete structure (RCC) is 52% complete.
Read full summary
Prabhat is a MHADA-sanctioned project by Shivam Parivar Developers Pvt Ltd in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800024145. It was launched in January 2020. It has 101 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 101 units, 69 are for sale and 32 are rehab units for existing members.
Possession was due in December 2025, after an extension of 2 years from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 52% complete, final finishes 3% complete.
47 units booked out of 69 units for sale (68%).