Paton Towers, Kandivali East
by Pravin Viram Satra · Kandivali East, Mumbai 400101 · Map
- Launched
- Feb 20206 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 529 of 53199% · 517 in Jul 2026
- Buildings
- 11.5 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 242
- 2 BHK
- 276
- Other units
- 13
- Total units
- 531
- Buildings
- 1
- Land
- 1.5 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 529 | |
| 100% | 25% | 0% | 517 | |
| 100% | 25% | 0% | – | |
| 100% | 25% | 0% | 283 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400101
Projects with 250–1,100 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 10 mths | 5 yrs 4 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Apr 2025 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 99% | 97% |
| MahaRERA complaints (filed by or against the builder) | 2 | 10 |
The 3 projects
- TW Gardens, Kandivali East
- Godrej Nest, Kandivali East
- Siennaa, Kandivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| TW Gardens | February 2020 | December 2027 | 100% | 414 units booked out of total 427 units |
| Godrej Nest | September 2019 | April 2025 | 100% | 552 units booked out of total 571 units |
| Siennaa | February 2019 | Mar 2024 – Dec 2027 | 98% | 526 units booked out of total 551 units |
About this project
Paton Towers by Pravin Viram Satra is a 531-unit SRA-sanctioned project in Kandivali East, Mumbai 400101, launched in February 2020 with possession due in December 2026. 529 units booked out of total 531 units. The concrete structure (RCC) is complete.
Read full summary
Paton Towers is an SRA-sanctioned project by Pravin Viram Satra in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800024618. It was launched in February 2020. It has 531 units in 1 building: 518 homes (1 and 2 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.
529 units booked out of total 531 units (99%). Since the July 2026 update, 12 more units have been booked and the reported concrete structure (RCC) has gone from 25% to 100%.