Hs Spring, Mulund East

Ready to moveLapsed

by Ashta Siddhi Constructions Private Limited · Mulund East, Mumbai 400081 · Map

Launched
Feb 20204 yrs 10 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
–
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
12
1 BHK
3
2 BHK
6
3 BHK
15
5+ BHK
1
Other units
15
Total units
52
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 70%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%–
100%100%90%–
100%100%70%50

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Hs Spring by Ashta Siddhi Constructions Private Limited is a 52-unit project in Mulund East, Mumbai 400081, launched in February 2020; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Hs Spring is a project by Ashta Siddhi Constructions Private Limited in Mulund East, Mumbai 400081, registered with MahaRERA as P51800024671. It was launched in February 2020. It has 52 units in 1 building: 37 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 5+ BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.