Landmark Divine, Borivali East

Lapsed

by S S Landmark Pvt Ltd · Borivali East, Mumbai 400066 · Map

Launched
Mar 20203 yrs 9 mths promised
Possession (MahaRERA)
Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
5
2 BHK
4
3 BHK
5
Total units
14
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%–
100%0%0%–
100%0%0%13

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Landmark Divine by S S Landmark Pvt Ltd is a 14-unit project in Borivali East, Mumbai 400066, launched in March 2020; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.

Read full summary

Landmark Divine is a project by S S Landmark Pvt Ltd in Borivali East, Mumbai 400066, registered with MahaRERA as P51800025174. It was launched in March 2020. It has 14 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.