- Launched
- Jul 20205 yrs 11 mths promised
- Possession (MahaRERA)
- Jun 2026Not extendedWhat does Lapsed mean?
- Concrete structure
- 80%Mid-construction
- Booked
- 41 of 7158% · 1 in Jul 2026
- Buildings
- 20.9 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 12
- 2 BHK
- 39
- 3 BHK
- 20
- Total units
- 71
- Buildings
- 2
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Reserved units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 83% | 80% | 30% | 41 | |
| 83% | 80% | 30% | 1 | |
| 83% | 80% | 30% | 1 | |
| 83% | 80% | 30% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Vivaana Heights by N K Builders & Developers is a 71-unit SRA-sanctioned project in Prabhadevi, Mumbai 400025, launched in July 2020; its MahaRERA registration has lapsed. 41 units booked out of total 71 units. The concrete structure (RCC) is 80% complete.
Read full summary
Vivaana Heights is an SRA-sanctioned project by N K Builders & Developers in Prabhadevi, Mumbai 400025, registered with MahaRERA as P51800025788. It was launched in July 2020. It has 71 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation 83% complete, structure (RCC) 80% complete, final finishes 30% complete.
41 units booked out of total 71 units (58%). Since the July 2026 update, 40 more units have been booked.