New Safalaya Chs Ltd, Bandra East
Ready to moveLapsed
by Amikrupa Land Developers Private Limited · Bandra East, Mumbai 400051 · Map
- Launched
- Jul 20208 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 4 yrs 9 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 10 of 3926%
- Buildings
- 11.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 39
- Total units
- 39
- Buildings
- 1
- Land
- 1.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 10 | |
| 100% | 100% | 95% | 10 | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
New Safalaya Chs Ltd by Amikrupa Land Developers Private Limited is a 39-unit BMC-sanctioned project in Bandra East, Mumbai 400051, launched in July 2020; its MahaRERA registration has lapsed. 10 units booked out of total 39 units. The concrete structure (RCC) is complete.
Read full summary
New Safalaya Chs Ltd is a BMC-sanctioned project by Amikrupa Land Developers Private Limited in Bandra East, Mumbai 400051, registered with MahaRERA as P51800025817. It was launched in July 2020. It has 39 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025, after an extension of 4 years 9 months from the original March 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
10 units booked out of total 39 units (26%).