Anutam, Andheri West

Lapsed

by Truly Highdreams Realtors LLP · Andheri West, Mumbai 400058 · Map

Launched
Aug 20203 yrs 1 mth originally promised
Possession (MahaRERA)
Sep 2026Extended by 3 yrsWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
31 of 5953% · 35 in Jul 2026
Buildings
10.9 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
38
2 BHK
21
Total units
59
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 90%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%31
100%0%0%35
90%0%0%13
50%0%0%3

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Anutam by Truly Highdreams Realtors LLP is a 59-unit SRA-sanctioned project in Andheri West, Mumbai 400058, launched in August 2020; its MahaRERA registration has lapsed. 31 units booked out of total 59 units. Work on the concrete structure (RCC) has not started.

Read full summary

Anutam is an SRA-sanctioned project by Truly Highdreams Realtors LLP in Andheri West, Mumbai 400058, registered with MahaRERA as P51800026032. It was launched in August 2020. It has 59 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2026, after an extension of 3 years from the original September 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.

31 units booked out of total 59 units (53%).