Navaghar Purvrang Coop Hs, Mulund East
Ready to moveLapsed
by Navghar Purvarang Chs Limited · Mulund East, Mumbai 400081 · Map
- Launched
- Aug 20204 yrs 10 mths originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 37 of 4288% · 76 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale37 booked out of 42 units
Rehab76 units for existing members
Total 118 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 20
- 2 BHK
- 58
- 3 BHK
- 40
- Total units
- 118
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 42
- Rehab units
- 76
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 37 | |
| 100% | 100% | 95% | 37 | |
| 100% | 100% | 95% | 37 | |
| 100% | 100% | 0% | 21 |
"–" means MahaRERA shows no figure for that update.
About this project
Navaghar Purvrang Coop Hs by Navghar Purvarang Chs Limited is a 118-unit MHADA-sanctioned project in Mulund East, Mumbai 400081, launched in August 2020; its MahaRERA registration has lapsed. 37 units booked out of 42 units for sale. The concrete structure (RCC) is complete.
Read full summary
Navaghar Purvrang Coop Hs is a MHADA-sanctioned project by Navghar Purvarang Chs Limited in Mulund East, Mumbai 400081, registered with MahaRERA as P51800026043. It was launched in August 2020. It has 118 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 118 units, 42 are for sale and 76 are rehab units for existing members.
Possession was due in June 2026, after an extension of 1 year from the original June 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
37 units booked out of 42 units for sale (88%).