Urban Waves, Bandra West

by Harekrushna Developers LLP · Bandra West, Mumbai 400050 · Map

Launched
Sep 20204 yrs 9 mths originally promised
Possession (MahaRERA)
Nov 2027Extended by 2 yrs 5 mths
Concrete structure
38%Mid-construction
Booked
21 of 3462% · 20 in Jul 2026
Buildings
11.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
5
2 BHK
5
3 BHK
24
Total units
34
Buildings
1
Land
1.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)38%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 20%Dec 2025: Concrete structure (RCC) 20%Jul 2026: Concrete structure (RCC) 37%Oct 2026: Concrete structure (RCC) 38%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 38%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%38%0%21
100%37%0%20
100%20%0%–
100%20%0%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400050

Projects with 10–70 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400050
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 9 mths4 yrs 2 mths
Possession date extendedBy 2 yrs 5 mths0 of 4
Possession date (MahaRERA)Nov 2027Oct 2024
Concrete structure (RCC)38%26%
MahaRERA complaints (filed by or against the builder)12

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Urban Waves by Harekrushna Developers LLP is a 34-unit SRA-sanctioned project in Bandra West, Mumbai 400050, launched in September 2020 with possession due in November 2027. 21 units booked out of total 34 units. The concrete structure (RCC) is 38% complete.

Read full summary

Urban Waves is an SRA-sanctioned project by Harekrushna Developers LLP in Bandra West, Mumbai 400050, registered with MahaRERA as P51800026269. It was launched in September 2020. It has 34 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is November 2027, extended by 2 years 5 months from the original June 2025. Construction: excavation complete, structure (RCC) 38% complete, final finishes not started.

21 units booked out of total 34 units (62%). Since the July 2026 update, 1 more unit has been booked, the reported concrete structure (RCC) has gone from 37% to 38% and the possession date has moved from June 2026 to November 2027.