Hirani Villa, Vile Parle East
Ready to moveLapsed
by Ami Infra Projects Private Limited · Vile Parle East, Mumbai 400057 · Map
- Launched
- Oct 20202 yrs 5 mths originally promised
- Possession (MahaRERA)
- May 2026Extended by 3 yrs 2 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 30 of 30100% · 22 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale30 booked out of 30 units
Rehab22 units for existing members
Total 52 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 25
- 3 BHK
- 15
- 4 BHK
- 1
- Other units
- 11
- Total units
- 52
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 30
- Rehab units
- 22
- Reserved units
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 30 | |
| 100% | 100% | 100% | 30 | |
| 100% | 100% | 99% | 30 | |
| 100% | 100% | 99% | 2 |
"–" means MahaRERA shows no figure for that update.
About this project
Hirani Villa by Ami Infra Projects Private Limited is a 52-unit SRA-sanctioned project in Vile Parle East, Mumbai 400057, launched in October 2020; its MahaRERA registration has lapsed. 30 units booked out of 30 units for sale. The concrete structure (RCC) is complete.
Read full summary
Hirani Villa is an SRA-sanctioned project by Ami Infra Projects Private Limited in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800026708. It was launched in October 2020. It has 52 units in 1 building: 41 homes (2, 3 and 4 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 52 units, 30 are for sale and 22 are rehab units for existing members.
Possession was due in May 2026, after an extension of 3 years 2 months from the original March 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
30 units booked out of 30 units for sale (100%).