Runwal Avenue, Bhandup East

by Susneh Infrapark Private Limited · Bhandup East, Mumbai 400042 · Map

Launched
Oct 2020First of 6 phases
Possession (MahaRERA)
Jun 2027 – Feb 2029Extended in 2 of 6 phases
Concrete structure
83%Weighted across 6 phases
Booked
1,344 of 1,92770%
Buildings
636.5 acres
MahaRERA complaints
13Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
599
2 BHK
937
3 BHK
286
4 BHK
1
Other units
104
Total units
1,927
Buildings
6
Land
36.5 acres
Phases
6
MahaRERA complaints
13

The 6 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Runwal Avenue Wing-J
Nearing possession
P51800026860351100%75%
Runwal Avenue Wing K
Nearing possession
P51800028811313100%79%
Runwal Avenue Wing - L
Mid-construction
P5180003189529579%69%
Runwal Avenue Wing - M
Mid-construction
P5180003351430952%65%
Runwal Avenue Wing - N
Mid-construction
P5180004771426079%43%
Runwal Avenue Wing - I
Mid-construction
P5180004823429584%82%
Show updates by phase

Runwal Avenue Wing-J (P51800026860)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%279
100%100%0%279
0%0%0%–
100%100%0%369

"–" means MahaRERA shows no figure for that update.

Runwal Avenue Wing K (P51800028811)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%269
100%100%0%269
100%100%0%228
100%100%0%329

"–" means MahaRERA shows no figure for that update.

Runwal Avenue Wing - L (P51800031895)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%79%0%215
100%62%0%215
100%39%0%–
100%30%0%314

"–" means MahaRERA shows no figure for that update.

Runwal Avenue Wing - M (P51800033514)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%52%0%216
100%34%0%216
100%22%0%–
100%19%0%322

"–" means MahaRERA shows no figure for that update.

Runwal Avenue Wing - N (P51800047714)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%79%0%112
100%68%0%112
100%68%0%–
100%50%0%79

"–" means MahaRERA shows no figure for that update.

Runwal Avenue Wing - I (P51800048234)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%84%0%253
100%74%0%253
100%25%0%–
100%25%0%175

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)83%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 81%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 56%Dec 2025: Concrete structure (RCC) 41%Jul 2026: Concrete structure (RCC) 74%Oct 2026: Concrete structure (RCC) 83%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 83%Final finishes 0%

How to read construction stages

About this project

Runwal Avenue by Susneh Infrapark Private Limited (Runwal) is a 1,927-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, registered with MahaRERA in 6 phases, with possession dates from June 2027 to February 2029. 1,344 units booked out of total 1,927 units. The concrete structure (RCC) is 83% complete.

Read full summary

Runwal Avenue is a BMC-sanctioned project by Susneh Infrapark Private Limited in Bhandup East, Mumbai 400042, registered with MahaRERA as 6 phases (P51800026860, P51800028811, P51800031895, P51800033514, P51800047714, P51800048234). The first phase was launched in October 2020. Together the phases have 1,927 units in 6 buildings: 1,823 homes (1, 2, 3 and 4 BHK) and 104 other units (shops, offices or not given by type), as registered with MahaRERA. All 6 phases are active on MahaRERA.

The phases' registered possession dates run from June 2027 to February 2029; 2 of 6 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 83% complete and final finishes 0% complete. 2 of the 6 phases have their structure complete.

1,344 units booked out of total 1,927 units (70%).

Runwal's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA46
Total units across these projects14,623
Completed without extending the possession date10
Completed after an extension5
Lapsed5
Under construction26
Possession date extended on the builder's application16
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Runwal projects343 (35 of 46 projects)