Runwal Avenue, Bhandup East
by Susneh Infrapark Private Limited · Bhandup East, Mumbai 400042 · Map
- Launched
- Oct 2020First of 6 phases
- Possession (MahaRERA)
- Jun 2027 – Feb 2029Extended in 2 of 6 phases
- Concrete structure
- 83%Weighted across 6 phases
- Booked
- 1,344 of 1,92770%
- Buildings
- 636.5 acres
- MahaRERA complaints
- 13Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 599
- 2 BHK
- 937
- 3 BHK
- 286
- 4 BHK
- 1
- Other units
- 104
- Total units
- 1,927
- Buildings
- 6
- Land
- 36.5 acres
- Phases
- 6
- MahaRERA complaints
- 13
The 6 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Runwal Avenue Wing-J Nearing possession | P51800026860 | 351 | 100% | 75% | |
| Runwal Avenue Wing K Nearing possession | P51800028811 | 313 | 100% | 79% | |
| Runwal Avenue Wing - L Mid-construction | P51800031895 | 295 | 79% | 69% | |
| Runwal Avenue Wing - M Mid-construction | P51800033514 | 309 | 52% | 65% | |
| Runwal Avenue Wing - N Mid-construction | P51800047714 | 260 | 79% | 43% | |
| Runwal Avenue Wing - I Mid-construction | P51800048234 | 295 | 84% | 82% |
Show updates by phase
Runwal Avenue Wing-J (P51800026860)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 279 | |
| 100% | 100% | 0% | 279 | |
| 0% | 0% | 0% | – | |
| 100% | 100% | 0% | 369 |
"–" means MahaRERA shows no figure for that update.
Runwal Avenue Wing K (P51800028811)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 269 | |
| 100% | 100% | 0% | 269 | |
| 100% | 100% | 0% | 228 | |
| 100% | 100% | 0% | 329 |
"–" means MahaRERA shows no figure for that update.
Runwal Avenue Wing - L (P51800031895)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 79% | 0% | 215 | |
| 100% | 62% | 0% | 215 | |
| 100% | 39% | 0% | – | |
| 100% | 30% | 0% | 314 |
"–" means MahaRERA shows no figure for that update.
Runwal Avenue Wing - M (P51800033514)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 52% | 0% | 216 | |
| 100% | 34% | 0% | 216 | |
| 100% | 22% | 0% | – | |
| 100% | 19% | 0% | 322 |
"–" means MahaRERA shows no figure for that update.
Runwal Avenue Wing - N (P51800047714)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 79% | 0% | 112 | |
| 100% | 68% | 0% | 112 | |
| 100% | 68% | 0% | – | |
| 100% | 50% | 0% | 79 |
"–" means MahaRERA shows no figure for that update.
Runwal Avenue Wing - I (P51800048234)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 84% | 0% | 253 | |
| 100% | 74% | 0% | 253 | |
| 100% | 25% | 0% | – | |
| 100% | 25% | 0% | 175 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Runwal Avenue by Susneh Infrapark Private Limited (Runwal) is a 1,927-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, registered with MahaRERA in 6 phases, with possession dates from June 2027 to February 2029. 1,344 units booked out of total 1,927 units. The concrete structure (RCC) is 83% complete.
Read full summary
Runwal Avenue is a BMC-sanctioned project by Susneh Infrapark Private Limited in Bhandup East, Mumbai 400042, registered with MahaRERA as 6 phases (P51800026860, P51800028811, P51800031895, P51800033514, P51800047714, P51800048234). The first phase was launched in October 2020. Together the phases have 1,927 units in 6 buildings: 1,823 homes (1, 2, 3 and 4 BHK) and 104 other units (shops, offices or not given by type), as registered with MahaRERA. All 6 phases are active on MahaRERA.
The phases' registered possession dates run from June 2027 to February 2029; 2 of 6 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 83% complete and final finishes 0% complete. 2 of the 6 phases have their structure complete.
1,344 units booked out of total 1,927 units (70%).
Runwal's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 46 |
|---|---|
| Total units across these projects | 14,623 |
| Completed without extending the possession date | 10 |
| Completed after an extension | 5 |
| Lapsed | 5 |
| Under construction | 26 |
| Possession date extended on the builder's application | 16 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Runwal projects | 343 (35 of 46 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.