Shantiniketan, Kandivali West
Ready to moveLapsed
by Namorealty And Infra LLP · Kandivali West, Mumbai 400067 · Map
- Launched
- Nov 20202 yrs originally promised
- Possession (MahaRERA)
- May 2025Extended by 2 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 19 of 4048%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 8
- 2 BHK
- 4
- 3 BHK
- 1
- Other units
- 27
- Total units
- 40
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 19 | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | 19 |
"–" means MahaRERA shows no figure for that update.
About this project
Shantiniketan by Namorealty And Infra LLP is a 40-unit project in Kandivali West, Mumbai 400067, launched in November 2020; its MahaRERA registration has lapsed. 19 units booked out of total 40 units. The concrete structure (RCC) is complete.
Read full summary
Shantiniketan is a project by Namorealty And Infra LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800026889. It was launched in November 2020. It has 40 units in 1 building: 13 homes (1, 2 and 3 BHK) and 27 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in May 2025, after an extension of 2 years 6 months from the original November 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
19 units booked out of total 40 units (48%).