Triumph Towers, Malad West
Ready to moveLapsed
by Triumph Builders LLP · Malad West, Mumbai 400064 · Map
- Launched
- Dec 20202 yrs 6 mths originally promised
- Possession (MahaRERA)
- May 2024Extended by 11 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 81 of 15353%
- Buildings
- 11.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 78
- 3 BHK
- 75
- Total units
- 153
- Buildings
- 1
- Land
- 1.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 81 | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 81 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400064
Projects with 70–350 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 6 mths | 4 yrs 11 mths |
| Possession date extended | By 11 mths | 2 of 3 |
| Possession date (MahaRERA) | May 2024 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Harshail Hornbill Apartment, Malad West
- Ajmera Arham, Malad West
- Samarth Reva, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Harshail Hornbill Apartment | May 2021 | December 2026 | 100% | – |
| Ajmera Arham | August 2021 | July 2027 | 83% | 166 units booked out of total 209 units |
| Samarth Reva | October 2021 | December 2026 | 100% | 82 units booked out of total 88 units |
About this project
Triumph Towers by Triumph Builders LLP is a 153-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in December 2020; its MahaRERA registration has lapsed. 81 units booked out of total 153 units. The concrete structure (RCC) is complete.
Read full summary
Triumph Towers is a BMC-sanctioned project by Triumph Builders LLP in Malad West, Mumbai 400064, registered with MahaRERA as P51800027364. It was launched in December 2020. It has 153 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in May 2024, after an extension of 11 months from the original June 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
81 units booked out of total 153 units (53%).