Mass Ionics, Andheri West

Lapsed

by Mass Buildsquare Structure Private Limited · Andheri West, Mumbai 400058 · Map

Launched
Dec 20205 yrs 6 mths promised
Possession (MahaRERA)
Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
81%Mid-construction
Booked (free sale)
38 of 5076% · 36 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale38 booked out of 50 units

Rehab36 units for existing members

Total 86 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
63
2 BHK
19
Other units
3
Total units
86
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
50
Rehab units
36
Reserved units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)81%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 35%Dec 2025: Concrete structure (RCC) 81%Jul 2026: Concrete structure (RCC) 81%Oct 2026: Concrete structure (RCC) 81%Dec 2024: Final finishes 0%Dec 2025: Final finishes 75%Jul 2026: Final finishes 75%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 81%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%81%75%38
100%81%75%38
100%81%75%38
100%35%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Mass Ionics by Mass Buildsquare Structure Private Limited is an 86-unit SRA-sanctioned project in Andheri West, Mumbai 400058, launched in December 2020; its MahaRERA registration has lapsed. 38 units booked out of 50 units for sale. The concrete structure (RCC) is 81% complete.

Read full summary

Mass Ionics is an SRA-sanctioned project by Mass Buildsquare Structure Private Limited in Andheri West, Mumbai 400058, registered with MahaRERA as P51800027417. It was launched in December 2020. It has 86 units in 1 building: 83 homes (1 RK, 1 BHK and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 86 units, 50 are for sale and 36 are rehab units for existing members.

Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 81% complete, final finishes 75% complete.

38 units booked out of 50 units for sale (76%).