Damji Shamji Business 78, Bhandup West

Ready to moveLapsed

by Fortune Construction Company · Bhandup West, Mumbai 400078 · Map

Launched
Dec 20203 yrs 6 mths originally promised
Possession (MahaRERA)
Jun 2025Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
58 of 7083%
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
70
Total units
70
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services94%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 54%Dec 2025: Final finishes 94%Jul 2026: Final finishes 94%Oct 2026: Final finishes 94%Excavation 100%Concrete structure (RCC) 100%Final finishes 94%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%94%58
100%100%94%58
100%100%94%58
100%100%54%57

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Damji Shamji Business 78 by Fortune Construction Company is a 70-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in December 2020; its MahaRERA registration has lapsed. 58 units booked out of total 70 units. The concrete structure (RCC) is complete.

Read full summary

Damji Shamji Business 78 is a BMC-sanctioned project by Fortune Construction Company in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800027593. It was launched in December 2020. It has 70 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 1 year from the original June 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 94% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

58 units booked out of total 70 units (83%).